Anfra is executing a full-scope BoP (Balance of Plant) contract for the Akkula Big Battery project, comprising both eBoP and cBoP. The Akkula Big Battery is one of Finland’s most significant BESS (Battery Energy Storage System) projects, and notably, it is the country’s first "four-hour battery."
eBoP = Electrical Balance of Plant
Sähkötekninen urakka, johon sisältyvät kaikki hankkeen vaatimat kaapeloinnit sekä virralle että tietoliikenteelle.
cBoP = Civil Balance of Plant
Rakennustekninen urakka, johon sisältyvät kaikki hankkeen vaatimat infratyöt mm. maarakennus, kunnallistekniikka ja perustukset.
We have already completed over 500 civil projects and possess a deep understanding of the unique demands of massive infrastructure undertakings. By combining this experience with our eBoP expertise, we provide the client with a secure and efficient partnership where the project's critical interfaces are managed seamlessly together.


